Report / Corridors

Hyderabad growth corridors: status report, October 2026

Where the Mumbai, Bangalore and Srisailam highway corridors stand: infrastructure, industry, jurisdiction and risk.

On this page

Key findings

  • Jurisdiction changed in March 2025: HMDA extended to the RRR, and FCDA created south of the ORR.
  • The RRR northern tender has been extended six times; the southern part is at DPR stage.
  • NIMZ at Zaheerabad reached infrastructure works in March 2026.
  • Operating industry is strongest at Kothur and around E-City; Foxconn at Kongara Kalan is reported operational.
  • No metro to Shadnagar or the Future City is sanctioned.

Corridor summary

CorridorEstablished anchorsMain planned itemsMain risks
Mumbai Highway (NH 65)Sangareddy industrial belt, IIT Hyderabad, Mahindra at ZaheerabadZaheerabad industrial city, RRR northAcquired NIMZ land, RRR delays
Bangalore Highway (NH 44)P&G and J&J at Kothur, NH 44, airportRRR southUnverified metro claims, industrial zoning
Srisailam Highway (NH 765)E-City, Maheshwaram parks, FoxconnFuture City, radial roads, new parksDual jurisdiction, Pharma City land, lakes

Methodology

Compiled from government statements, official documents and news reports listed under Sources, as of October 2026. No price or transaction data is included.

Transaction trends Data pending

A future edition will add registered-transaction analysis.

Published: 10 October 2026

Sources

  1. Telangana Today: RRR tender
  2. Siasat: NIMZ works
  3. nri2nri: G.O. 68 and 69
  4. Swarajya: Metro Phase II
Content typeReport: Where can I go deeper?
StandardsEditorial policy
Found an error?Report a correction

Tell us what you’re looking for

We will identify suitable plotted developments based on your requirements and help arrange site visits. Read first, decide at your own pace.